    I would like to know if there is any regulatory issues and or code to convert a 30 Ton Punch Press from relay control to PLC.
    We converted a Brake to a Punch Press to punch holes in aluminum.

  2. #2
    Inactive Member bigrockk's Avatar
    Join Date
    September 29th, 2002
    Posts
    146
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    You may have to have the machine recertified by a testing laboratory such as Entela,Intertek Canada, Underwriters Laboratories or CSA or some other lab that is Accredited to do this.
    Check with your local AHJ, they should be able to tell you what is required.
    Good luck

  3. #3
    Inactive Member doninis's Avatar
    Join Date
    April 25th, 2005
    Posts
    2
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    thank you Bigrockk, I contacted the the elect. equipment inspector and was told to go ahead and
    make the modification and then call for a re-inspection. Simple as that...

  4. #4
    Inactive Member Navyguy's Avatar
    Join Date
    April 22nd, 2004
    Posts
    14
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    Something else that you may want to check with is the H&S people. When I have converted equipment from relay to PLC, etc the existing guarding systems and operating mechanism were no longer valid. Things like double palm buttons and light curtains need to be installed along with other safety related equipment.

  5. #5
    Inactive Member Tony Moscioni's Avatar
    Join Date
    June 4th, 2002
    Posts
    59
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Arrow

    Rule 2-004 Permit
    Electrical contractors or others responsible for the carrying out of the work shall obtain a permit from the inspection department before commencing work with respect to installation, alteration, repair, or extension of any electrical equipment.

    Electrical installation means the installation of any wiring in or upon any land, building, or premises from the point or points where electric power or energy is delivered therein or thereon by the supply authority or from any other source of supply, to the point or points where such power or energy can be used therein or thereon by any electrical equipment and shall include the connection of any such wiring with any of the said equipment, and any part of the wiring aforesaid, and shall also include the maintenance, alteration, extension, and repair of such wiring;

    Rule 2-016 Current-Permits
    Except as provided in Rule 2-018, no reconnection, installation, alteration, or addition shall be connected to any service or other source of electric energy by a supply authority, electrical contractor, or other person, until a current-permit authorizing the supply of electric energy thereto has been obtained from the inspection department.

    ?Pre-Start Health and Safety Reviews?

    A Pre-Start Health and Safety Review is required if, in a factory other than a logging operation, a provision from the regulation and the circumstances described exist,

    a. When a new apparatus, structure or protective element is to be constructed, added or installed or a new process is to be used; or

    b. When an existing apparatus, structure, protective element or process is to be modified and one of the following steps must be taken to obtain compliance with the applicable provision:

    1. New or modified engineering controls are used.

    2. Other than new or modified measures are used.

    3. A combination of new, existing or modified engineering controls and other new or modified measures is used

    If a Pre-Start Health and Safety Review is required, the owner, lessee or employer shall ensure the following:

    (a) The apparatus, structure, or protective element is not operated or used, unless the review has been conducted, and

    (b) All measures identified in the review as being required for compliance with the relevant provisions of this Regulation listed in Table 1 have been taken, and

    (c) If some or all of the measures specified in (b) are not taken, the owner, lessee or employer shall provide written notice to the joint health and safety committee or the health and safety representative, if any, of what measures have been taken to comply with the relevant provisions of Regulation 851 that are listed in Table 1.

    A Pre-Start Health and Safety Review includes the preparation of a written report that is made to the owner, lessee or employer and contains,
    The details of the measures to be taken for compliance, and

    (a) If testing is required before the apparatus or structure can be operated or used or before the process can be used, details of measures to protect the health and safety of workers that are to be taken before the testing is carried out.

    A Pre-Start Health and Safety Review shall have the following:
    (a) Date and signature, and

    (b) The report bears a professional engineer seal.

    All reports of Pre-Start Health and Safety reviews conducted under this Regulation shall:
    (a) Be kept readily accessible in the workplace together with any supporting documents, and

    (b) Be provided to the joint health and safety committee or the health and safety representative, if any, before the apparatus, structure or protective element is operated or used or the process is used.


    Tony Moscioni
    Electrical Inspector
    Electrical Safety Authority

  6. #6
    Inactive Member Handasee's Avatar
    Join Date
    May 21st, 2004
    Posts
    1
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    Take a look as CSA Z142-02. It covers a lot about presses.